1、Software Project TrackingA CMM Level 2Key Process AreaSoft Tech Development Inc.天马行空官方博客:http:/ ;QQ:1318241189;QQ群:1755696321Soft Tech Development Inc.PurposeThe purpose of Software Project Tracking and Oversight is to provide adequate visibility into actual progress so that management can take effe

2、ctive actions when the projects performance deviates significantly from the plans.Software Project Tracking and Oversight involves tracking and reviewing the accomplishments and results against documented estimates, commitments, and plans, and adjusting these plans based on the actual accomplishment

3、s and results.天马行空官方博客:http:/ ;QQ:1318241189;QQ群:1755696322Soft Tech Development Inc.GoalsGoal 1 Actual results and performances are tracked against the software plans.Goal 2Corrective actions are taken and managed to closure when actual results and performance deviate significantly from the softwar

4、e plans.Goal 3Changes to software commitments are agreed to by the affected groups and individuals.3Soft Tech Development Inc.CommitmentA project software manager is designated to be responsible for the projects software activities and results.The project follows a written organizational policy for

5、managing the software project.4Soft Tech Development Inc.AbilityA software development plan for the software project is documented and approved.The project manager explicitly assigns responsibility for work products and activities.Adequate resources and funding are provided for tracking the software

6、 project.The managers are trained in managing the technical and personnel aspects of the project.First-line managers receive orientation in the technical aspects of the project.5Soft Tech Development Inc.Activities1.A documented software development plan is used for tracking the software activities

7、and communicating status.2.The projects software development plan is revised according to a documented procedure.3.Software project commitments and changes to commitments made to individuals and groups external to the organization are reviewed with senior management according to a documented procedu

8、re.6Soft Tech Development Inc.Activities4.Approved changes to commitments that affect the software project are communicated to the members of the software engineering group and other software-related groups.5.The size of the software work products (or size of the changes to the software work product

9、s) are tracked, and corrective actions are taken as necessary. The projects software effort and costs are tracked, and corrective actions are taken as necessary.7Soft Tech Development Inc.Activities6.The projects critical computer resources are tracked, and corrective actions are taken as necessary.

10、7.The projects software schedule is tracked, and corrective actions are taken as necessary.8.Software engineering technical activities are tracked, and corrective actions are taken as necessary.9.The software risks associated with cost, resource, schedule, and technical aspects of the project are tr

11、acked.8Soft Tech Development Inc.Activities10.Actual measurement data and replanning data for the software project are recorded.11.The software engineering group conducts periodic internal reviews to track technical progress, plans, performance, and issues against the software development plan.12.Fo

12、rmal reviews to address the accomplishments and results of the software project are conducted at selected project milestones according to a documented procedure.9Soft Tech Development Inc.MeasuresMeasurements are made and used to determine the status of the software tracking and oversight activities

13、.Examples of measurements include:effort and other resources expended in performing the tracking and oversight activities; andchange activity for the software development plan, which includes changes to size estimates of the software work products, software cost estimates, critical computer resource

14、 estimates, and schedule.10Soft Tech Development Inc.VerificationThe activities for project tracking and oversight are reviewed with senior management on a periodic basis.The activities for project tracking and oversight are reviewed with the project manager on both a periodic and event-driven basis

15、.The software quality assurance group reviews and/or audits the activities and work products for project tracking and oversight and reports the results.11Soft Tech Development Inc.Coverage Goal 1Actual results and performance are tracked against the plansThe software group uses the project plan AC 1

16、 and conducts periodic internal reviews AC12 to track: product size AC 5 effort and cost AC 6 critical computer resources AC 7 project schedule AC 8 technical activities AC 9 project risks AC 10Measurement and re-planning data are recorded AC 11Formal reviews are help at key milestones AC 1312Soft T

17、ech Development Inc.Coverage Goal 2Corrective actions are taken and managed to closureThe following are tracked and corrective actions taken: product size AC 5 effort and cost AC 6 critical computer resources AC 7 project schedule AC 8 technical activities AC 9Measurement and re-planning data are re

18、corded AC 11The project plan is revised using a documented procedure AC 213Soft Tech Development Inc.Coverage Goal 3Changes to commitments are agreedCommitments and changes to commitments with external groups are reviewed with senior management using a procedure AC 3Approved changes to commitments are communicated to the software team and other affected groups AC 414Soft Tech Development Inc.Review Actions15Soft Tech Development Inc.Software Project TrackingA CMM Level 2Key Process AreaSoft Tech Development Inc.16Soft Tech Development Inc.