150814 MS for footing excavation.docx

上传人:marr****208 文档编号:132118731 上传时间:2020-05-12 格式:DOCX 页数:11 大小:59.70KB
返回 下载 相关 举报
150814 MS for footing excavation.docx_第1页
第1页 / 共11页
150814 MS for footing excavation.docx_第2页
第2页 / 共11页
150814 MS for footing excavation.docx_第3页
第3页 / 共11页
150814 MS for footing excavation.docx_第4页
第4页 / 共11页
150814 MS for footing excavation.docx_第5页
第5页 / 共11页
点击查看更多>>
资源描述

《150814 MS for footing excavation.docx》由会员分享,可在线阅读,更多相关《150814 MS for footing excavation.docx(11页珍藏版)》请在金锄头文库上搜索。

1、HY/2013/12Tuen Mun-Chep Lap Kok Link-Northern Connection Toll Plaza & Associated Works Method Statement Construction of Footing of Falsework For Portal Beam ConstructionContract No:HY/2013/12Project Title:Tuen Mun-Chek Lap Kok Link-Northern Connection Toll Plaza & Associated WorksMethod Statement Co

2、nstruction of Footing of FalseworkFor Portal Beam ConstructionDocument No:MSSF/M/00xxRevision:00Date:14 August 2015Method Statement Construction of Footing of FalseworkFor Portal Beam ConstructionDocument No:MSSF/ M/00xxRevision:00Date:14 August 2015Revision HistoryRevision No.DescriptionRevised ByD

3、ate00First Submission14 August 2015Method Statement Construction of Footing of FalseworkFor Portal Beam ConstructionDocument No:MSSF/M/00xxRevision:00Date:14 August 2015Checked by:PositionSignatureNameDateSite AgentJohn WongHead of ConstructionRoger CheungConstruction ManagerEric KwokPrepared by:ACM

4、Liu HailongTable of Content1.0 Introduction2.0 Scope of works3.0 Sequence and methods of works4.0 Plant and equipment employed5.0 Risk concern6.0 Environment concern7.0 Appendix1.0 IntroductionThe method statement describes the methodology for the construction of footing of falsework which will be e

5、rected temporarily for the portal beam construction of TD1 decking. The construction sequence and methods to be employed are outlined in the method statement. The plants and equipments to be employed for the works, and related safety and environmental concerns are also involved.2.0 Scope of works2.1

6、 LocationThe footings to be built are along the two sides of eastbound Lung Mum Road. The designed location of each footing is determined by the existing utilities underground, especially 132kV high voltage cables. The actual position and dimension of each footing might be adjusted on site to suit t

7、he existing utilities. The general layout of footing is attached in Appendix 1.2.2 OrganizationParticulars of responsible / Key personnel:NameCompanyResponsibilityContact No.John WongCKJVSite Agent9094 9900Roger CheungCKJVHead of Construction9156 0746Eric KwokCKJVConstruction Manager6761 3188Liu Hai

8、longCKJVAssistant Construction Manager5335 0102HY TangCKJVEnvironmental Officer9670 0777Winson ChungCKJVSafety Manager9323 1588Leonard YuengCKJVGraduate Engineer6200 4257Everd ZhangCKJVForeman9200 54262.3 References2.3.1 Detailed Design Drawings:NTP/D/TD1/6121, 6122, 611161172.3.2 Relevant reference

9、d documents:Section 7 of General Specification for Civil Engineering Works, 2006 EditionSection 7 of Particular Specification for Contract No. HY/2013/123.0 Sequence and methods of works3.1 Setting OutThe proposed location of footings should be set out by survey team in advance. The engineer shall c

10、heck the location before any excavation works start, making sure it meets the design intentions.3.2 Preparation worksa) Clear the area of the designated for footing properly. Relocate the water filled barriers when necessary, but in any case the water barriers shall not invade into the road markings

11、 of the carriageway.b) Partly divert the passenger footpath, keep the footpath in tidy with a minimum width of 1.2m. c) Provide adequate barriers and warning sign/tags at the accesses to prevent public other than site personnel from entering the site.3.3 Trial Trench Excavationa) Two trenches from b

12、oth ends of the footing, with the size of 0.5m wide, 1.5m long and 1.5m deep shall be dug firstly by hand. b) Electric breakers shall be used if the surface of the trench consists of man-made hard material (e.g. concrete, shotcrete, etc.).c) When UU is found within the trial trench, the UU shall be

13、identified and protected properly.d) Material excavated from the trenches shall be properly stockpiled and covered over.e) The excavation should be completed in a period as short as possible to avoid water accumulating in the trench in case of raining.3.4 Excavation and Lateral Supporta) The excavat

14、ion of footing shall be cut vertically manually or by light machinery. b) When support of excavation is needed, installation of timber boards, excavation and insertion of walings and struts shall proceed by stages until the full excavation depth is achieved.c) Machinery should be used with caution,

15、to prevent instability or movement of road base of adjacent pavement. Operation shall be stopped immediately when any signs of excessive instability or movement are observed. Investigation and strengthening works shall be carried out before resumption of excavation works.d) The material excavated shall be safely stockpiled for reuse or removal and