1、V. Construction Site Coordination Management1. Construction General Layout Plan CoordinationBased on construction deployment and milestone delivery requirements in various phases, General Contractor is in charge of formulating overall plan for general layout plan and deliver technical disclosure to

2、subcontractors for carrying out dynamic management.General contractor is responsible for dispatching road, temporary storage yard, fixed storage yard within construction site unitedly.The subcontractor shall submit “temporary access road or storage yard application sheet to General contractor as per

3、 production requirements at each stage for approval by procedures.The subcontractor shall submit “Use of existing fixed storage yard application sheet” (Sheet 7-2) to General Contractor Production Coordination Department as per production requirements at each stage for approval.The subcontractors ar

4、e responsible for standardized management and maintenance of public facilities, surrounding roads within fixed storage yard or temporary site they used, as well as to cater for General Contractors standardized management requirements.2. Temporary Water and Power Supply CoordinationGeneral Contractor

5、 is in charge of overall planning and implementation for temporary water and power supply deployment and deliver technical disclosure to subcontractors.The subcontractors are in charge of configuring full-time temporary water and power supply managerial personnel, who should submit to General Contra

6、ctor “Subcontracting use power general schedule” within stipulated period, as well as to sign “ Temporary water and power use management agreement” with General Contractor within one week.The subcontractor shall submit “Use of temporary power supply application” to General Contractor Production Coor

7、dination Department as per production requirements at each stage for approval.The subcontractors are in charge of safety management of temporary water and power use and accept daily inspection from General Contractor, as well as rectify the discovered problems during inspection and make reply immedi

8、ately.3. Temporary Facilities CoordinationGeneral Contractor is in charge of overall planning and implementation for temporary facilities, formulating usage allocation scheme and deliver technical disclosure to subcontractors.The subcontractor shall submit “Use of temporary facilities (office, livin

9、g) application sheet” to General Contractor Production Coordination Department as per production requirements at each stage for approval.The subcontractors are in charge of maintain and manage temporary facilities use and accept daily inspection from General Contractor, as well as rectify the discov

10、ered problems during inspection and make reply immediately.The subcontractors are in charge of applying overall acceptance and handover to General Contractor after temporary facilities usage completed.4. Material and Equipment Mobilization and Demobilization Coordination The subcontractors shall sub

11、mit detailed material, equipment mobilization application schedule in accordance with General Contractors construction progress to confirm material, equipment name, specification, model and mobilization time.The subcontractors are in charge of material mobilization and demobilization, who shall prep

12、are documents which include, but not limited to, material type, transportation mode, quality assurance, etc. as well as submit “Material/equipment mobilization and demobilization application sheet” to General Contractor Production Coordination Department for approval.The subcontractors are in charge

13、 of abide by General Contractors site material and equipment management system, pile up mobilized material and equipment in good order, accept daily inspection from General Contractor, as well as rectify the discovered problems during inspection and make reply immediately.5. Vertical Transportation

14、CoordinationGeneral Contractor is in charge of overall planning and implementation for vertical transportation equipment, formulating project vertical transportation scheme and deliver technical disclosure to subcontractors.The subcontractors shall submit “ Subcontract vertical transportation equipm

15、ent use schedule sheet” to General Contractor for approval.The subcontractor shall submit “Use of vertical transportation application sheet” to General Contractor Production Coordination Department every day as per daily construction demand for approval.General Contractor is in charge of planning al

16、l subcontractors vertical transportation equipment use situation as a whole and formulating and public “Daily use distribution sheet of vertical transportation equipment” , as well as coordinate and resolve emergent problems among subcontractors for using vertical transportation equipment.The subcontractors are in charge of configure full-time staff to manage vertical transportation within subcontractors and cooperate General Contractor