《老挝政府采购系统评估报告》由会员分享,可在线阅读,更多相关《老挝政府采购系统评估报告(22页珍藏版)》请在金锄头文库上搜索。
1、 Lao PDR NATIONAL PUBLIC PROCUREMENT SYSTEM ASSESSMENT REPORT Procurement Monitoring Office Ministry of Finance Lao PDR March 2006 Lao PDR: National Public Procurement System Assessment Report TABLE OF CONTENTS INTRODUCTION APPROACH AND METHODOLOGY . 1 TEAM MEMBERS 2 ASSESSMENT RATINGS 3 BIS ASSESSM
2、ENT 4 SUMMARY OF FINDINGS 4 RECOMMENDATIONS . 6 Short Term Recommendations . 7 Medium Term Recommendations . 15 Long Term Recommendations 18 ANNEXES . 20 Lao PDR: National Public Procurement System Assessment Report 1 Introduction Approach and Methodology The assessment of the public procurement sys
3、tem of Lao Peoples Democratic Republic (PDR) was conducted using the Baseline Indicators System (BIS) for measuring the quality of a countrys procurement policies and institutional capacity, which was developed by the joint World Bank and Organisation for Economic Co- operation and Development (OECD
4、) Development Assistance Committee (DAC) Procurement Roundtable.1 As such, the assessment was undertaken on the basis of four (4) key areas called “Pillars,” which are composed of twelve (12) Indicators that have been identified as the core components of a public procurement system. These twelve (12
5、) Indicators are, in turn, composed of Baselines that are considered the desirable standards against which the existing elements of Lao PDRs public procurement system may be assessed. For the assessment, points were given to each Baseline, the total of which corresponds to weights assigned to each o
6、f the Indicators. In turn, the weights of these Indicators comprise the total score for each of the four (4) Pillars. To reflect their equal importance, each of the Pillars was given a weight of twenty-five percent (25%) each, amounting to a grand total of one hundred percent (100%). These points an
7、d weights were discussed with, and agreed upon by, the Procurement Monitoring Office (PrMO), Ministry of Finance (MOF) of the Government of Laos (GOL), so that the distribution thereof would be based upon the importance and relevance of each of the Baselines and Indicators involved, in relation to t
8、he GOLs public procurement reform program. In conducting the BIS assessment, a review of Lao PDRs public procurement legislative and institutional framework had to be undertaken. This review included the following: 1. The Decree of the Prime Minister on Government Procurement of Goods, Construction,
9、 Maintenance and Service, dated 9 January 2004 (the “Procurement Decree”); 2. The Implementing Rules and Regulations on the Decree of Government Procurement of Goods, Works, Maintenance and Services, specifically Ministry of Finance No. 0063/MOF, dated 12 March 2004 (IRR); and 3. The structure and o
10、perations of the PrMO, as well as its charter the Decision of the Minister on the Establishment of the Procurement Monitoring Office, specifically Ministry of Finance No. 2382/MOF, dated 4 November 2004 (the “PrMO Charter”). Lao PDRs Budget Law and its recently enacted Anti-Corruption Law were also
11、considered during the discussions. 1 The World Bank (Operations and Country Services), Increasing the Use of Country Systems in Procurement, p. 5 (March 2005). Lao PDR: National Public Procurement System Assessment Report 2 In order to provide field data for the BIS assessment, a national consultant
12、 visited the following key institutions to interview officials therein and, when possible, gather data and documentation: 1. Ministry of Agriculture and Forestry (MAF); 2. Ministry of Communications, Transportation, Posts and Construction (MCTPC); 3. Ministry of Education (MOE); 4. Ministry of Healt
13、h (MOH); 5. Vientiane Capital; and 6. Electricite du Laos (EDL), a State-Owned Enterprise. The PrMO plans to have two (2) more institutions visited, in order to conduct further interviews and gather data that may be used for the BIS assessment. The BIS weight distribution and the initial findings we
14、re presented to the GOL Procurement Technical Working Group (TWG) for review and further confirmation during a meeting held on 22 February 2006, at the PrMO office. A Validation Workshop was held on 10 March 2006, at the International Cooperation and Training Center (ICTC), Vientiane Capital, to fur
15、ther validate the findings of this BIS Report. The participants of the Validation Workshop were technical experts and representatives of key institutions including those approached for this Report as well as those represented in the GOL Procurement TWG. Professional associations and private companie
16、s involved in GOL goods and civil works procurements were invited to gather their views and comments on the Report, but did not attend. The institutions/agencies that were represented during the Validation Workshop were: 1. MOH; 2. MOE; 3. MCTPC; 4. MOF; 5. MAF; 6. Ministry of Foreign Affairs (MOFA); 7. Vientiane Capital; 8. State Inspection Authority (SIA); 9. Lao Telecommunications (LTC) (a State-Own