{教育管理}碾压混凝土施工专业外语.

上传人:精****库 文档编号:138479132 上传时间:2020-07-15 格式:DOC 页数:50 大小:48.63KB
返回 下载 相关 举报
{教育管理}碾压混凝土施工专业外语._第1页
第1页 / 共50页
{教育管理}碾压混凝土施工专业外语._第2页
第2页 / 共50页
{教育管理}碾压混凝土施工专业外语._第3页
第3页 / 共50页
{教育管理}碾压混凝土施工专业外语._第4页
第4页 / 共50页
{教育管理}碾压混凝土施工专业外语._第5页
第5页 / 共50页
点击查看更多>>
资源描述

《{教育管理}碾压混凝土施工专业外语.》由会员分享,可在线阅读,更多相关《{教育管理}碾压混凝土施工专业外语.(50页珍藏版)》请在金锄头文库上搜索。

1、8 RCC as a New Construction Method(RCC作为一种新的施工方法)8.1 General Construction Considerations (一般情况下施工过程需考虑的因素)There are considerable differences between vertical, block-by-block construction (垂直块状浇筑)of dams with conventional mass concrete and horizontal, lift-by-lift construction(水平通仓浇筑)of dams with RCC

2、. The construction plant for RCC is usually, less costly, and utilized at a higher capacity factor (利用率)than that required for conventional concrete gravity dams. But the fast pace of placement required to achieve the economies possible with RCC imposes a greater discipline (要求)on the planning, sche

3、duling(进度), and coordination(协调) in the field between designer(设计) and contractor(承包商).The RCC design approaches described in Chaps. 4, 5, and 6 diverge(不同点在于.) in some construction procedures. In all cases, however, the mixing(拌合), transporting(运输), spreading(摊铺), and compacting (碾压)of relatively l

4、arge volumes of material are concentrated into a short time interval. In the United States, the time limit from mixing plant to final compaction is about 45 min. It is about twice that in Japan. In addition, the Japanese RCD method requires that lifts be cured (养护)for as long as 36 h before placemen

5、t (浇筑)of the next layer of RCC. In the United states and elsewhere, the goal has nearly always been to come as close as possible to continuous placement of RCC. 8.1.1 SchedulingConstruction scheduling for RCC is less forgiving than for mass concrete(大体积混凝土). Although some mix designs can have greate

6、r tolerances than conventional concrete, RCC is still a sensitive concrete and the critical path (关键路线)for placing RCC is focused on completing one lift at a time. There are no alternate monolithic (整块的、独块的)blocks to form or place while problems are being analyzed.To avoid costly delays over dispute

7、s on specification(规范)compliance(执行), the authority to resolve engineering problems must be vested in a well trained field organization. Lines of communication between the project engineer(项目工程师)and contractor must be clearly established and used frequently. Clarity(廉洁), candor(坦诚), and cooperation

8、are very important in achieving the speed of placement possible with RCC.Thorough field and classroom training of construction crews(施工队伍)and inspectors(检查员) in the handling and placement of RCC is essential. Lean, dry RCC mixes resemble damp(潮湿的) gravel(砂砾石)and are often placed by road-building or

9、earth-dam crews using earthmoving equipment. However, all the desired characteristics of the product are those of concrete. Meeting the specifications requires educating workers to the specific requirements of RCC as a new construction material requiring specific construction methods.Because so much

10、 depends on fast, efficient placement of the RCC, all related activities such as foundation cleanup, access, assembly of embedded components(预埋件), and stockpiling (贮存、堆存)of materials must be meticulously planned and scheduled well before construction starts. Construction of forms and assembly of emb

11、edded items should be planned and scheduled so that as much of the work as possible is done off the dam, or if necessary, from the top of a lift (升程)during shift(工作班)changes.Lift scheduling is often complicated by concerns over heat buildup. Because the production rate of RCC can be very high, contr

12、ols to limit thermal cracking(温度裂缝)may restrict the season or time of day that placement is allowed as well as the rate of placement.At Upper Stillwater Dam, all of the RCC was placed during a five-month weather window each year from May to October and only during two 8-h shifts starting at 8 p.m. T

13、his was necessary in order to keep placement temperatures below the 50oF (10oC) specification limit. At Willow Creek and Galesville dams, placement was limited to no more than three and four lifts, respectively, each 24 h.Conversely, at Elk Creek and Stagcoach dams, the contractor was encouraged to

14、place RCC as fast as possible. At peak placement, six 1-ft (0.3-m) lifts were placed in a day at Stagecoach. The 150-ft-high (46-m) dam required 44,500 yd3 (34,000 m3) of RCC which was placed during 37 days in the summer of 1988. To keep placement temperatures low at Elk Creek, the specifications re

15、quired that the most massive sections be constructed during the late winter and early spring.8.2 Aggregate Production and Plant Layout (砂石料生产和混凝土工厂布置)Maintaining adequate supplies of acceptable aggregate is particularly important to RCC scheduling. More than half of the aggregate required for an ent

16、ire construction season may need to be stockpiled well ahead of the start of construction in order to keep up with extraordinarily high demand during the placement season. This can also provide some easing(缓解)of cash flow(现金流)and scheduling requirements during the placement season. Large stockpiles also allow for more economical sizing of production facilities and for blending of material that may be out of specification. If precooling of aggregate

展开阅读全文
相关资源
正为您匹配相似的精品文档
相关搜索

最新文档


当前位置:首页 > 商业/管理/HR > 企业文化

电脑版 |金锄头文库版权所有
经营许可证:蜀ICP备13022795号 | 川公网安备 51140202000112号