12February1999

上传人:桔**** 文档编号:568709512 上传时间:2024-07-26 格式:PPT 页数:12 大小:163.50KB
返回 下载 相关 举报
12February1999_第1页
第1页 / 共12页
12February1999_第2页
第2页 / 共12页
12February1999_第3页
第3页 / 共12页
12February1999_第4页
第4页 / 共12页
12February1999_第5页
第5页 / 共12页
点击查看更多>>
资源描述

《12February1999》由会员分享,可在线阅读,更多相关《12February1999(12页珍藏版)》请在金锄头文库上搜索。

1、This presentation will probably involve audience discussion, which will create action items. Use PowerPoint to keep track of these action items during your presentationIn Slide Show, click on the right mouse buttonSelect “Meeting Minder”Select the “Action Items” tabType in action items as they come

2、upClick OK to dismiss this boxThis will automatically create an Action Item slide at the end of your presentation with your points entered.Levan BabukhadiaLevan BabukhadiaD D Collaboration Meeting Collaboration Meeting, October 11 - 13, 2000, Fermilab, October 11 - 13, 2000, FermilabStatus of the L1

3、 TriggerStatus of the L1 TriggerSUNY at Stony BrookSUNY at Stony BrookD Collaboration Meeting, October 11 - 13, 2000, FermilabLevan BabukhadiaCTPT/FPS ComponentsCTPT/FPS ComponentsAnalog (Fermilab - D)AFE-8MCM (primarily CFTax): 10 here, ready by 11/01, 54 more by 12/15, balance 01/30/01Crates/Cable

4、s on hand, installed when requiredPower supplies delayed until new year (partial).Mixer ( Fermilab - CD )Super-sector (1/5th) mid-NovemberFull Mixer 1/01Digital ( Fermilab - D )All MBs here and in testingTransition boards expecting in 2 weeksCTPT DBs (single-wide, 5 Virtex 2.5v FPGAs) by mid-Novembe

5、r FPS DBs (double-wide, 3 Virtex 2.5v FPGAs) partial order outXilinx/Virtex FPGAs for CTOT on order, others held until further decision, Virtex vs. Virtex-ECrates/Cables/PS all here by mid-NovemberD Collaboration Meeting, October 11 - 13, 2000, FermilabLevan BabukhadiaCTTP/FPS Firmware: CFT/CPS Axia

6、lCTTP/FPS Firmware: CFT/CPS AxialDFEA (80) : Jamieson Olsen (Kin is gone)Both L1/L2 firmware in good shape4 FPGAs find tracks in 4 Pt and report to 5-th FPGA and to MuonBackend (5-th) FPGA does CPS cluster finding and track matchingfirmware has to be re-written, concerns on the chip sizeexpect funct

7、ional and tested firmware in a couple of monthsCTOC (8) : Juan Lizarazo, now Ricardo Rodrigez Both L1/L2 firmware completed and tested in testbenchMinor issues and additions will be addressed by Ricardo/ManuelCTQD (4) : Pavel Polozov now goneL2CFT part completed functionally with some minor issueNee

8、ds implementation, L2CPS, and all of this tested in the hardwareCTTT (1) : Jerry BlazeyAlgorithm/VHDL/Functional/Implementation at 20%2 out of 64 Trigger Terms done through the implementation phaseL1-L3 sender, finish all VHDL, implementation, hardware test standD Collaboration Meeting, October 11 -

9、 13, 2000, FermilabLevan BabukhadiaCTTP/FPS Firmware: CPS StereoCTTP/FPS Firmware: CPS StereoDFES (5) : Qichun Xu, MSUNo link to L1 TM, straight to L2 and L3, thus has time!Main issue is cluster finding in the large number (500) of CPS stereo strips in a sector but having time may save the day.New M

10、SU student Qichun Xu, just startedMade a good head-start with an overall algorithms and the cluster finding algorithms in particular Start writing VHDL, expect functional code in about 1-2 monthsCPSS (2) : ?!Nobody yet! Perhaps Qichun will take on this one as well .D Collaboration Meeting, October 1

11、1 - 13, 2000, FermilabLevan BabukhadiaCTTP/FPS Firmware: FPSCTTP/FPS Firmware: FPSDFEF (32) : Levan BabukhadiaChallenge: cluster finding in 144 FPS strips at the L1 rateL1 U/V algo developed, coded, and implemented; test stand is nextL1U and L1V each takes Xilinx/Virtex 400 FPGA (75%, 63 MHz)Develop

12、 L2 priority reporting algo to take care of truncation. It is aimed at the 3rd FPGATransferring clusters within a DB or find clusters anew?.FPSS (4) : Mrinmoy BhattacharjeeL1 algo developed, coded, and implemented w/o the L3 senderfits in one Xilinx/Virtex 400 FPGA (30%, 66 MHz)Develop L2 algorithmF

13、PTT (1) : Satish DesaiL1 algo developed, coded, and implemented w/o the L3 senderfits in one Xilinx/Virtex 400 FPGA (20%, 64 MHz)Complete all L1 functionally, test stand by the end of OctoberD Collaboration Meeting, October 11 - 13, 2000, FermilabLevan BabukhadiaCTPT/FPS Installation/CommissioningCT

14、PT/FPS Installation/CommissioningAssembling test stands for digital/VHDL testingHardware: 2 PCs, MBs, 2 Data Pump Boards, PS, cables, CTPT/FPS DBs1 fully stuffed double-wide DB10 fully stuffed single-wide DBsPersonnel: Jamieson Olsen, Brian Connolly (very short time), Ricardo Rodrigez, and a new par

15、t-time techHad 1 working test stand but recently moved to DAB3/NE; will be made operational this week Aiming at having 2 “single board” bench-tops and 1 “multi-board” test stand (for a one sparse system test - available now, Jamieson)Installing cables/crates on platformCrates/Cables installed in MCH

16、D Collaboration Meeting, October 11 - 13, 2000, FermilabLevan BabukhadiaComponentsScintillator (48) completeCAF boards (175) on handCompleting ADC (12) board layout, ordering partsVertex board, FPGA 75% complete, layout commencingProcuring signal cables (60) soonCrate/PS on handInstallation/Commissi

17、oningInstalled scintillator (4/00) Cabling awaits FPS, commissioning thereafter Software/FirmwareWorking on embedded softwareDownload currently underwayDatabase under developmentSchedule (on time)Electronics installed, February 1; Lum Monitoring March 1And/Or terms, March-AprilLuminosity Monitor Sta

18、tusLuminosity Monitor StatusD Collaboration Meeting, October 11 - 13, 2000, FermilabLevan BabukhadiaTiming signal generation and distributionSome work has been done and some tests have been madeInitial implementation will probably cover just the CC racksL2/L3 readout complete (by November)Uses much

19、of the same equipment as the readout from the TFAll circuit boards exist and initial designs of all the FPGAs existAnalog input circuit (pick-off) boards (320) Prototypes of this exist and some testing has been done1FTE month to productionQuadrant Terms Circuit board (40) and FPGA design work has be

20、en startedNo prototypes exist yetWill not be pushed in the immediate futureSchedule (late but well before 3/01)Inactive until TF complete 11/00. Resume within a monthStart with analog pick-offsL1 Calorimeter Trigger StatusL1 Calorimeter Trigger StatusD Collaboration Meeting, October 11 - 13, 2000, F

21、ermilabLevan Babukhadia L1MU Hardware (4 crates, prod beginning UAz)Crate Manager (MTCM)Production card testing in progressMotherboard (MTCxx - Trigger Card) Production cards beginning fabricationFlavor Boards Production Trigger Manager (MTM) boards ready for fabricationProduction wire DB (MTC10) de

22、sign in progress (finish in 2 weeks) Preproduction scintillator DB (MTC05) in fabricationSLDBs (Gbit/s Serial Links)Production board testing in progress Software/FirmwareDownload infrastructure in placePreproduction versions of all firmware existNo alarms, monitoringL1 Muon Trigger StatusL1 Muon Tri

23、gger StatusD Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia MCEN Hardware (5 crates, in preprod testing BU)Crate Manager (MCCM)Preproduction card layout in progressCentroid Finder Cards (MCEN) Preproduction card testing in progressPhysics Boards (MCPB)Preproduction board test

24、ing in progress InfrastructureCustom VME backplanes completedPower suppliesPrototype assembled and testedVICOR supplies ordered but with 20-22 week lead timePlatform Services - on hold pending final cable plant designCabling (1,600)Production at Fermilab and NIU in progressL1 Muon Trigger StatusL1 M

25、uon Trigger StatusD Collaboration Meeting, October 11 - 13, 2000, FermilabLevan Babukhadia Near Term Commissioning GoalsMid-AugustStable operation of one (sparse) L1MU trigger crate and the L1MU MTM cratestill using preproduction cardsEarly OctoberAdd L1CTPT MTM crate to the aboveMid-OctoberBegin co

26、mmissioning production of L1MU crates and cards Longer Term Commissioning GoalsBegin full crate testing in late Dec or early JanTwo octant triggering until thenMCEN cards 2 months behind aboveTemporary power supplies for full crate testsL1 Muon Trigger StatusL1 Muon Trigger StatusD Collaboration Mee

27、ting, October 11 - 13, 2000, FermilabLevan BabukhadiaAll equipment operational and installedDefective SCL cables are being repairedL3 readoutFinish up making readout to L3 available for normal use (by 1/11)Master Clock synchronization with the Tevatron beamThis work now startingOperational permitNee

28、d to install 5 fuse blocks and write the documentationL1 Specific Trigger Fired Mask to L2Needed to make the Pseudo-Terms workDeferred until some progress on getting L1 Cal Trigger running againFirmwareCompletion of pseudo-termsCommissioning run-controlPersonnelMajor loss of two engineers. Replacement uncertainTrigger Framework StatusTrigger Framework Status

展开阅读全文
相关资源
正为您匹配相似的精品文档
相关搜索

最新文档


当前位置:首页 > 办公文档 > 工作计划

电脑版 |金锄头文库版权所有
经营许可证:蜀ICP备13022795号 | 川公网安备 51140202000112号