1、现浇重力式钢筋混凝土挡土墙Cast in place gravity reinforced concrete retaining wallConstruction technology standards (VIII, 124)1 scope of applicationThis standard is applicable to the construction of cast in place reinforced concrete retaining wall for highway, urban road and bridge.2 construction preparation2.1

2、 materials2.1.1 cement: generally use Portland cement, ordinary portland cement, slag Portland cement. Cement approach should have product certification and inspection report, deal with the strength, stability and other performance indicators after entering the necessary sampling reexamination, the

3、quality must be consistent with current national standards Portland cement and ordinary portland cement GB175. When there is any doubt about the quality of the cement or the cement is out of production for more than three months, the re examination must be conducted before use and the result shall b

4、e used as a result of the retest. Different kinds of cement shall not be used in combination.2.1.2 sand: generally use medium and coarse sand. Sand varieties, quality should be consistent with current national standard technical specification for construction of highway bridges and culverts JTJ041,

5、after entering the country in accordance with the provisions of the current standard test methods of aggregate for Highway Engineering JTJ058 sampling test.2.1.3: we should use the hard stone or pebble gravel, should according to the different situations of origin, category, processing methods and s

6、pecifications, in accordance with the provisions of the current national standard test methods of aggregate for Highway Engineering JTJ058 batch inspection, the quality should be consistent with current national standard highway bridge culvert construction technology standard JGJ63 regulations.2.1.4

7、 water: suitable for drinking water. When using other water sources, the water quality should be in line with the current national standard water standard for concrete mixing, JGJ63.2.1.5 steel: steel shall have quality certificate and test report form; variety, level, specifications of steel bars s

8、hould comply with the design requirements; the reinforced approach should be selected to do sample test of mechanical properties, the quality must be consistent with existing national standards, the reinforcement of concrete hot rolled round bar GB13013, the reinforcement of concrete hot rolled ribb

9、ed bar GB1499 and GB13788 cold rolled ribbed steel bars and other provisions.Chemical analysis or other special tests shall be carried out when the steel bars are found to be brittle, poor in weldability or mechanical properties are abnormal.2.1.6 welding electrode: the selected electrode should be

10、matched with the reinforced base material, and the approach should have a certificate.2.1.7 admixture: additives should be product manuals, factory inspection reports and certificate of quality, performance testing report, the content of harmful substances should be tested by the corresponding level

11、 of testing issued by the testing department. Approach shall be re examined by sampling, and the suitability of admixture and cement shall be checked. The quality and application technology of the admixture shall be in line with the current national standard concrete admixture, GB8076 and regulation

12、s on the application of concrete admixtures, GB50119.2.1.8 admixture: the admixture shall have the factory certificate or quality certificate and the quality inspection report provided by the statutory inspection unit, and shall be re examined after the approach. The quality of the admixture shall b

13、e in accordance with the current relevant standards of the state, and the amount of admixture shall be determined by experiment.2.1.9 embedded parts specification and material shall comply with the design requirements.2.2 implements and equipment2.2.1 machinery: concrete mixer, concrete pump (pump b

14、y using), concrete mixer truck, hoisting machine, cutting machine, bending machine, welding machine, crane, dump trucks, scales, mobile generator.2.2.2 tools: steel plate, trolley, scraper, level, foot, shovel, vibrator and so on.2.3 operating conditions2.3.1 the main structure of the bridge is comp

15、leted or the elevation of the subgrade is higher than the elevation of the foundation of the retaining wall, and the compactness can meet the design requirements before construction can be carried out.2.3.2 base acceptance and complete the hidden inspection procedures.2.4 technical preparation2.4.1

16、the road and bridge design drawings shall be checked before construction, and the surveying personnel shall calculate the retaining wall plane and Gao Cheng control survey and construction survey according to the construction line and the Gao Cheng control point of the road, the bridge construction line and the control point.2.4.2 complete breakdown of commencement report, co