卧式水轮发电机组安装工艺

上传人:鲁** 文档编号:470302349 上传时间:2023-06-25 格式:DOC 页数:6 大小:54.50KB
返回 下载 相关 举报
卧式水轮发电机组安装工艺_第1页
第1页 / 共6页
卧式水轮发电机组安装工艺_第2页
第2页 / 共6页
卧式水轮发电机组安装工艺_第3页
第3页 / 共6页
卧式水轮发电机组安装工艺_第4页
第4页 / 共6页
卧式水轮发电机组安装工艺_第5页
第5页 / 共6页
点击查看更多>>
资源描述

《卧式水轮发电机组安装工艺》由会员分享,可在线阅读,更多相关《卧式水轮发电机组安装工艺(6页珍藏版)》请在金锄头文库上搜索。

1、卧式水轮发电机组安装工艺Horizontal hydro-generating unit installation process卧式水轮发电机组的安装分为预埋部份(管路)、导水机构(主机)、轴承部份、基础部份、发电机部份、辅助设备。The installation of the horizontal hydro-generating unit is divided into embedded part(piping), distributor ( main unit), bearing part, foundation part, generator part, auxiliary part

2、. 一、 水轮发电机组埋件预埋 Hydro-generating unit embedded part根据工程进度的要求与土建配合对所需的油、气、水管路进行预埋,对所有埋设的管路的管口进行封堵,防止异物进入。Embed the needed oil, gas, water piping according to the project process and civil engineering. Plug all the pipe orifices of the piping embedded to keep foreign matters from getting into.二、 测点放样

3、Measuring point layout根据按甲方提供的高程按设计图纸来确定机组的三维坐标,方法可用水准仪或钢琴线连通器原理来保证机组中心、高程与X、Y坐标。According to the height provided by owner and the design drawing to determine the unit three-dimension coordinate, and the unit center, height and X、Y coordinate can be guaranteed with balance level or the law of piano

4、line connected vessels. 三、 进水部份的安装The installation of the water inlet part把阀门、伸缩节和进水弯管依次吊入预留的机坑内,用法兰连接,即阀门与伸缩节连接,伸缩节与进水弯管连接,并校正前后左右位置和安装高程,下部加临时支撑固定,用水准仪吊线法校正进水弯管法兰面高度和中心线位置,主要是校正进水弯管的水平、垂直度和中心高。Successively lift valve, expansion joint, water inlet elbow into the reserved pit. Use flange to connect

5、valve and expansion joint, expansion joint and water inlet elbow, then adjust the position and installation height, temporary supports are fixed at the bottom. Balance level plumbing method is adopted to check the water inlet elbow flange surface height and center line position, mainly to check the

6、level, verticality and center height.蝶阀在没安装凑合节前做好蝶阀静态的全开、全关调整工作,并检查在关闭状态的密封情况,在全开时阀门是否在中间位置,必要时给予适当的调整。Before butterfly valve installed with the expansion joint, carry out the all open, all closed adjustment work at the static state, check the seal situation at the closed state, check whether valve

7、is in the middle position at the all open state, then adjust if necessary. 四、 导水机构的安装(蜗壳)The installation of distribution(spiral casing)金属蜗壳的安装是卧轴混流式水轮机安装中的一个重要环节,由于导水机构是整机出厂,所以可以整体同时安装。将蜗壳吊装就位后,蜗壳进水口与进水法兰面对好,加石棉橡胶垫套上螺栓拧紧,并穿上地脚螺栓,加临时支撑,为了保证蜗壳的位置正确必须做到以下三点:(1)蜗壳整体中心高程(2)蜗壳整体水平(3)蜗壳整体X、Y垂直度。The metall

8、ic spiral casing installation is the important part during horizontal Francis turbine installation. Install the distributor integrally, since distributor is out of factory in one piece. When the spiral casing is lifted into position, check spiral casing water inlet and water inlet flange face, pad t

9、he asbestos rubber gasket and tighten the bolts, fix with foundational bolt, use temporary support. In order to ensure the accuracy of the spiral casing position, the following three points should be fulfilled: One, the unity center height of the spiral casing. Two: spiral casing unity level. Three:

10、 spiral casing unity X、Y verticality. 两台蜗壳就位后将采用橡胶水平器、钢琴线、框式水平仪吊线法等工艺,使精度达到优良标准。同时检查导水机构、导水叶的开口,立面间隙、端面间隙,做好静态手动开关机的调整,运动时无卡阻现象,并加以调整,完成上述工作后,点焊牢固,准备二期混凝土浇灌。When the two spiral casings are put into position, use rubber level device, piano line, frame type level suspension method to make the accuracy

11、 meet the excellent standard. Check the distributor, the opening of the guide vane, vertical face gap, end face gap, adjust the manual start and shutdown at the static state, non- obstruction in operation. After the above adjustment, spot-weld tightly, and prepare the stage 2 concrete placing.五、 基础底

12、板的埋设与调整The embedment and adjustment of the foundational base plate根据两台导水机构中心以及机组X、Y十字线基准点来确定基础板位置,调整高程、水平,用垫片、楔子板来保证。Determine the foundational plate position as the center of the two distributors and the unit X、Y reticle benchmark, adjust the height and level, use gaskets, wedge board to ensure.以转轮

13、室中心为基准,来定位定子基础板中心、高程以及X、Y坐标。方法为基础底板中心线与钢琴线重合,用角尺测量基础板与钢琴线的高程,要求比设计值略低051mm,用调整铁调整达到要求后,用电焊牢固基础板,固定地脚螺栓,拧上螺母。再按上述方法复查中心、高程、水平有无变化,必要时再作调整,直到符合要求。Consider the benchmark as the runner room to locate the state foundation plate center, height and X、Y coordinate. The method is coincide the foundation base

14、 plate center line and piano line, measure the height of the foundation plate and piano line with angle rule, the value should be lower 051mm than design value. After adjusting with adjustable iron to meet the requirement, weld the foundation plate with electrical welding, fix the foundation bolt, f

15、ix the nut. Recheck the center, height and level as above method, adjust if necessary. 六、 轴承座的安装The installation of the bearing seat将所有轴承座吊放在基础板上并在组合面上按图纸规定加金属垫片及绝缘板,轴承座就位后进行调整,用水平仪、钢琴线调整检查,调整轴承使轴承与机组中心、水平、高程相对应。调整后,紧固基础螺栓,以防移位。Lift the bearing seat on the foundation plate, and pad with the metal sp

16、acer and insulation plate on the combination face. Adjust when bearing seat is in the position, check with level device and piano line. Adjust the bearing until it matches the unit center, level and height. By preliminary adjustment, fix the foundation bolt to prevent movement.七、定子和转子的安装 The installation of the stator and rotor1、将定子底座用方木垫高,并拆除发电机轴伸端的轴承座。 Raise the state bottom with square timber,