Construction procedure for Pre Testing

上传人:pu****.1 文档编号:456125517 上传时间:2023-01-24 格式:DOC 页数:11 大小:206KB
返回 下载 相关 举报
Construction procedure for Pre Testing_第1页
第1页 / 共11页
Construction procedure for Pre Testing_第2页
第2页 / 共11页
Construction procedure for Pre Testing_第3页
第3页 / 共11页
Construction procedure for Pre Testing_第4页
第4页 / 共11页
Construction procedure for Pre Testing_第5页
第5页 / 共11页
点击查看更多>>
资源描述

《Construction procedure for Pre Testing》由会员分享,可在线阅读,更多相关《Construction procedure for Pre Testing(11页珍藏版)》请在金锄头文库上搜索。

1、East-west Gas Pipeline ProjectConstruction procedure for Pre TestingChina Petroleum Pipeline Bureau(CPP)Document No.: EWPL00-COS-PR-0014Rev.: A1 Construction procedure for Pre TestingContract No.:Document No.: A12006-6-17ISSUED FOR REVIEWDu Zhongyuan Zeng ZhaochengLi JianhuiREVDATEDESCRIPTIONPREPARE

2、D BYREVIEWED BYCHECKED BYAPPROVED BYPage 1 of 7Contents 1. General32. Procedures33. HSE64. Quality Assurance6Page 2 of 71.0 General1.1ScopeThis procedure provides a detailed method of pre testing for 48” East-west Gas Pipeline Project in Indian. 1.2References1.2.1Company documentEWP100-P30-J00-513 S

3、pecification for Bored CrossingsEWP100-P30-J00-509 Specification for Flushing, Gauging and Hydro testingEWP100-P30-J00-505 Specification for Pipeline WeldingEWP100-P30-J00-506 Specification for Construction of PipelineEWP100-P30-J00-515 Specification for Dewatering and Pre-commissioning1.2.2Project

4、documentsC-70-P-Q-0006-00 Project HSE PlanC-70-P-Q-0002-00 Construction Quality Control Plan2.0 Procedures2.1 Hydrostatic pre-test execution 2.1.1 Temporary pressure test system The pipe spools shall be welded and tested above ground in proper and safe location as approved by Company. Each string sh

5、all be fitted with test ends and filled with water supplied through tankers. Filling shall be carried out from the lowest point and venting air from the highest point (see sketch below).1/2” branch pressure test pipePressure test pumpPressure gaugeEllipse end capWater filling pumpVenting air valveWa

6、ter draining valvePipe spool under pressure testing2” branch pressure test pipe试压支管Pipe support blockTest headerThermometer2.1.2 Filling Water and Venting Air While opening air vent valve, water filling pump shall start filling till water overflow from venting valve, closing the valve and stop the w

7、ater filling pump.To let air in the pipe vent out completely, water shall be filled at lower point and air shall be vented at high point of tested pipe. 2.2 Pipe Test 2.2.1 Preparation of Pressure Test All the temporally facilities connected with pipe shall be inspected All the instruments have been

8、 calibrated (pressure gauges, ambient and pipe thermometers.Water purity.Test headers have been pre-tested.2.2.2 Pressurization Test Pressurization test shall be performed in three phases as follows: 1150% Pt75% PtTime (h)Pt4In the chart:Pt is test pressurel The First Phase:Pressurization test shall

9、 be performed with pressure test pump which the constant rate not exceeding 2 bars/min, and stop pressurization till pressure reach 50% of test pressure. Stabilization of pressure shall be held for 15 minutes, and continue pressurize after checking the tested pipe without abnormal status. l The Seco

10、nd Phase: The constant rate should not exceed 2 bars/min, and the pressure stop when reach 75% of the test pressure. Stabilization of pressure shall be held for 15 minutes, and continue pressurize after checking the tested pipe without abnormal status. l The Third Phase:When the pressure reach 100%

11、of test pressure, pressurization shall be stopped and held for 4 hours minimum.2.2.3 Acceptance criteria:The hydrostatic test shall be considered as positive if pressure has kept a constant value throughout the test duration.2.3 TerminationAfter the positive result of testing and all the data have b

12、een gathered, the test shall be terminated upon written approval given by the Company. The pipeline shall be slowly depressurised at a moderate and constant rate as instructed by Company. Subsequent operations such as dewatering, installation of sectionalising valves, pre-commissioning checks and co

13、mmissioning shall be carried out as per the applicable specifications enclosed with the Contract.All thermocouples installed in the pipeline shall be removed and damaged coating shall be repaired using Company approved materials and procedure.In the event of failure, the pipe / section removed from

14、the installed pipeline shall be kept aside and preserved for further investigation of the reasons for failure.After successful testing the ends of the pipeline section shall be capped and buried unless immediate tie-in is carried out. The location of the ends shall be marked on ground by installing

15、markers.3.0 HSEl During testing operation, Contractor shall ensure that adequate measures are taken to safe guard all personnel and equipment working in close proximity to the testing operations and to safe guard the general public. These measures shall comprise: The testing crew shall follow the pro