DOCKSpecification for APL Qingdao建造方针 船舶

上传人:jiups****uk12 文档编号:39443898 上传时间:2018-05-15 格式:DOC 页数:48 大小:212.50KB
返回 下载 相关 举报
DOCKSpecification for APL Qingdao建造方针 船舶_第1页
第1页 / 共48页
DOCKSpecification for APL Qingdao建造方针 船舶_第2页
第2页 / 共48页
DOCKSpecification for APL Qingdao建造方针 船舶_第3页
第3页 / 共48页
DOCKSpecification for APL Qingdao建造方针 船舶_第4页
第4页 / 共48页
DOCKSpecification for APL Qingdao建造方针 船舶_第5页
第5页 / 共48页
点击查看更多>>
资源描述

《DOCKSpecification for APL Qingdao建造方针 船舶》由会员分享,可在线阅读,更多相关《DOCKSpecification for APL Qingdao建造方针 船舶(48页珍藏版)》请在金锄头文库上搜索。

1、M.V APL QINGDAODOCKING SPECIFICATIONS001 GENERAL INFORMATION 100GENERAL SERVICES200SURFACE PREPARATION AND PAINTING 300DOCK WORK 400HULL CONSTRUCTION 500DECK MACHINE & EQUIPMENT 600 NAVIGATION EQUIPMENT 700 SAFETY EQUIPMENT 800 MACHINERY PARTICULARS 900 DRY DOCKING 1000 MAIN ENGINE 1100 AUXILARY ENG

2、INES & MACHINERY 1200 ELECTRICAL EQUIPMENT 1300 PERFAMANCE TEST001. GERAL INFORMATIOM1.NAME : M.V APL QINGDAO2.OWNER : S.K.F MARITIME,S.A3.TYPE :CONTAINER CARRIER4.BUILT : KOYO DOCKYARD 22ND MAR 19955.HULL NO. : S20526.FLAG : PANAMANIAN7. IMO No. : 91226058.CALL SIGN : H9HX9.CLASS : N.K / No.9517291

3、0. LOA : 299.84M11. LPP : 283.00 M12. BM : 37.20M213. DM : 21.80 M14. DRAFT(Summer) : 13.025M15. LIGHT SHIP : 24711GT D:4.868M16. GROSS TONNAGE : 58923 GT17. NETT TONNAGE : 24651GT18. DWT(Summer) : 61489GT19. MAIN ENGIN : Mitsui-B&W 10K90MC M.C.O 59600PS x 94.0rpm20. GENERATORS : Yanmar 6N280L-GN 4S

4、ETS2350PS x 720rpm: Turbo Generator Mitsubishi AT52C 1SET1500KW x 11729/1800 rpm x 1SET: SHAFT GEN./MOTOR G/1200KW M/960KW x 1SET21. AUX. BOILER : Mitsubishi Vertical Cylindrical MC-140A 14000kg/h x 7.0Kg/cm222. EXH GAS ECONOMIZER: Mitsubishi Dual Pressure TypeH.P 6040kg/h x 6.5kg/cm2L.P 2180kg/h x

5、3.5kg/cm2S.H 5340kg/h x 6.0kg/cm2100 GENERAL SERVICES1. DRY DOCKINGDry dock and undock the vessel for examination, survey, and any repair of hullrudder, propeller, cleaning and painting.Vessel to be placed on suitability arranged blocks.1ST : 2daysExtra : 5days Divers for adjusting blocks: Additiona

6、l blocks:2. MOORING & UN-MOORING Moor and unmoor the vessel include the yards arranged tugboats, dock Pilotand installing and removing gangways.1st Mooring for berthing on arrival1st Un-mooring for Docking32nd Mooring for Un-docking2ND Un-Mooring for Sailing3. WHARFAGE Mooring the vessel alongside w

7、harf.Total: 15days4. FIRE HOSE To be arranged fire hoses at 2 places on deck and 1 place in E/R while the vessel is in dry dock or without power. Total: 22daysConnection & disconnection: 1time5. FIRE WATCHMANTo be arranged fire watchman during repairs, especially when hot work is in progress. Additi

8、onal fire watchman for hot working should be taken the confirmation from the attending superintendent.Total: 22days6. COOLING SEA WATER To be arranged cooling seawater lines for domestic reefer plant, while the vessel is in dry dock or without power. To be connected to Drain cooler for Boiler Operat

9、ion and windlass before un-docking, if necessary.Total: 7daysConnection & disconnection: each 1time7. SHORE POWER To be supplied shore power during the vessel is in dry dock.Electrical power: 440V x 400A x 60Hz x 3P x 40000KWConnection & disconnection: 1time ( Shore connection box )8. GAS FREE CERTI

10、FICATE To be issued gas free certificate when man entry or hot work to be carried out in tanks and enclosed spaces.9. GARBAGE CONTAINERS4To be arranged on upper deck in consultation with the C/O and to be cleared daily. To issue garbage discharged certificate by yard.10. FRESH WATER to be supplied b

11、y C/Os request.F.W.T(P): 150m3D.W.T(S): 150m3Connection & disconnection: 2times11. BALLAST WATER to be supplied the following tanks to make undocking draft. Air vent pipe bonnet and covers to be removed and refitted. Last time un-docking condition. 1. F.P.T: 185M/T 2. No.1 W.B.T 1046M/T 3. No.2 W.B.

12、T(P) 1172M/T 4. No.3 W.B.T (S) 1172M/T Total: 3575M/T Connection & disconnection: 1time x 3lines 12. BILGE & SLUDGE to be landed up from the E/Room by yards potablepump. Manhole covers operation by crew hand.To provide removal certificate by yardBilge: 20m3 Sludge: 20m3Pump: 1set Chief engineer prio

13、r to arrival at dockyard should make empty tank for bilgereserve tank, bilge well and waste oil tank as possible as he can.13. To provide 2 line of TELEPHONE between shore office and vessel.Total: 22days (Domestic only)14. To arrange LIGHTING in tanks as requested by attending superintendent.15. To

14、provide portable VENTILATION FANS as requested by attendingsuperintendent.516. To supply COMPRESSED AIR for general use and testing while vessel is in dry dock or without power.Total: 7daysConnection & disconnection: 1time17. To provide SHORE CRANE for lifting ships stores, spare parts, provisions a

15、rranged by Owner.Total: 5hours18. GENERAL CLEANING to be carried out vessels deck, accommodationspace, cargo hold, engine room and area where repairs had been carried out.19. PLASTIC SHEETING to be fitted in the following places by crew hand. -Accommodation Alleyways on Upper & A-deck -Engine Control Room -Deck office 20. To carry out SEA TRIAL on completion of all repairs.To be provided sea transportation for trail.Total: 3hours 21. Engine room SKY LIGHT (Bolted hatch) to be opened and closed.22. CLASS SURVEY (HULL & MACHINERY) 1

展开阅读全文
相关资源
正为您匹配相似的精品文档
相关搜索

最新文档


当前位置:首页 > 行业资料 > 其它行业文档

电脑版 |金锄头文库版权所有
经营许可证:蜀ICP备13022795号 | 川公网安备 51140202000112号