1、计算实例:(作业)M.V. Brodie Arrived 0600 Hrs Wednesday 9th JuneN.O.R. Tendered 1100 Hrs Wednesday 9th JuneLoading Commenced 0700 Hrs Thursday 10th JuneLoading Completed 1200 Hrs Tuesday 15th June Vessel sailed 2100 Hrs Tuesday 15th June Cargo loaded 20,000 metric Tonnes Grain in Bulk Lay time to commence a

2、t 1300 Hrs if notice given before noon. At 0700 Hrs next working day if given after noon, notice to be given in ordinary working hours (0900-1700 Hrs Monday to Friday). Cargo to be loaded at the rate of 5,000 metric Tonnes per weather working day of 24 consecutive hours. Time from 1700 Hrs Friday or

3、 the day preceding a holiday to 0800 Hrs Monday, or next working day not to count unless used, but only actual time used to count, unless vessel already on demurrage. Demurrage rate $5,000 per day pro rata/despatch rate at half demurrage rate on lay time saved. Other salient notes: Normal port worki

4、ng hours 0700-1700 Monday to Friday. Working outside aforementioned normal hours is available on overtime basis. On Monday 14th June rain stopped work in the port from 0900-1000 Hrs. The vessels owners agreed an overtime shift from 0700-1600 Hrs on Saturday 12th June. The vessels sailing was delayed

5、 due to an engine problem on 15th June.答案:单位名称 编号_Messr_ 日期 Date_船名 M.V._Brodie_装/卸货种及吨数 Loading/Discharging_20,000_metric tons of_Grain in Bulk _时间 Time日期 Date星期 Day递交装卸准备就绪通知书时间 Notice of Readiness Tendered: 1100 Hrs Wednesday 9th June接受装卸准备就绪通知书时间 Notice of Readiness Accepted:装卸时间起算时间 Laytime Com

6、menced to Count: 1300 Hrs Wednesday 9th June开始装卸时间 Loading/Discharging Commenced: 0700 Hrs Thursday 10th June装/卸货完毕时间 Loading/Discharging Completed: 1200 Hrs Tuesday 15th June 货物装/卸率 Rate of Loading/Discharging: 5,000 MT per W.W.D. of 24 consecutive hours日期 星期 时间 Hours 说明 可用时间 实用时间 节省/滞期时 间Date Day

7、of the Week From to DescriptionLaytime allowed D H MLaytime used D H M Time saved/lost D H M9th June Wednesday O600 Arrived 0 0 09th June Wednesday 1100 N.O.R. Tendered 0 0 09th June Wednesday 1300 Laytime commence 0 0 09th June Wednesday 1300 2400 Laytime count 11 11 010th June Thursday O000 2400 L

8、aytime count 24 24 011th June Friday O000 1700 LOADING 17 17 011th June Friday 1700 2400 not to count 0 0 012th June Saturday O000 O700 not to count 0 0 012th June Saturday O700 1600 overtime work 9 9 012th June Saturday 1600 2400 not to count 0 0 013th June Sunday O000 2400 not to count 0 0 014th J

9、une Monday O000 O700 not to count 0 0 014th June Monday O700 O900 Actual LOADING 2 2 014th June Monday O900 1000 rain 0 0 014th June Monday 1000 2400 LOADING 14 14 015th June Tuesday O000 1200 LOADING Complete 12 12 015th June Tuesday 1200 1900Allowed time used up7 0 7速遣/滞期费率 合计 96 Hours 89 hours 7Rate of Despatch/Demurrage: Total速遣/滞期费总金额Total Amount of Despatch/Demurrage: Despatch: 25007/24=729 USDFor and behalf of the Shippers As Agents