精品您需要多少人来支持SAP项目?1

上传人:精****库 文档编号:133103292 上传时间:2020-05-24 格式:DOC 页数:3 大小:53.04KB
返回 下载 相关 举报
精品您需要多少人来支持SAP项目?1_第1页
第1页 / 共3页
精品您需要多少人来支持SAP项目?1_第2页
第2页 / 共3页
精品您需要多少人来支持SAP项目?1_第3页
第3页 / 共3页
亲,该文档总共3页,全部预览完了,如果喜欢就下载吧!
资源描述

《精品您需要多少人来支持SAP项目?1》由会员分享,可在线阅读,更多相关《精品您需要多少人来支持SAP项目?1(3页珍藏版)》请在金锄头文库上搜索。

1、附件三:您需要多少人来支持SAP项目?众所周知,实施R/3费用很高,但是长期支持费用有多少?请用下文中Gartner的rules of thumb 来算一下,如果采用SAP系统你需要多少人来支持?与您原来估算的差距有多大?同高昂的长期支持费用相比,初期实施费用根本算不了什么!原文: Managing Enterprise Applications: From Packages To Productivity , GartnerGroup Europe Symposium proceedings, Cannes, France, November 2-5, 1998, Fred Magee资料来

2、源:To develop a rough estimate for the size of an ERP implementation staff, usefive person months per concurrent user and normalize based on estimatedproject length.SAP Implementation Staff % By RoleRoles Avg % Range %ESP Avg %When UsedTraining-Methodology31-1220Technical Architecture71-2747Gap Analy

3、sis30-1428Module Configuration6140-8224Interfaces7 0-3542Custom Extensions5 0-2138Data Conversion60-1841Testing/QA8 4-1922Total Staff Size Coarse Rule of Thumb : 5 Person-Months per Concurrent UserSource: Gartner Measurement Selected Benchmark DataNote : ESP = Enterprise Service Providers, eg Big Si

4、xs and large SIsThere is no correct size for an ERP implementation team, there are simplytoo many variables involved. However, having said that some data is betterthan none. Using twelve selected Gartner Measurement SAP benchmarks, thevariability in staffing quickly becomes apparent. Core implementa

5、tion teamsizes ranged from 24 to 161 with implementation elapsed times ranging from10 to 48 months. No obvious meaningful correlation was present in the data, e.g. number of modules, number of instances, degree of customizationor number of interfaces. However, looking back at the implementation usin

6、goperational concurrent users as a metric, a correlation was found. Acoarse rule of thumb is 5 person months per concurrent user. Estimationsof project duration and concurrent users would lead to an overall estimatefor staff size. A rough approximation for concurrent users would be 1:6named users.Fo

7、r the 8 staff roles measured, the data indicates a wide range of usage,with configuration dominating share of staff. Approximately half the casesused ESP for certain roles and when they did the averages indicatedsignificant portions of work being outsourced. (.)Staffing sizes vary widely by organiza

8、tion, but can be correlated to two keyparameters, concurrent users and the industry standard Unix metricSPECmark92 benchmark.SAP Support Staff EFT MetricsApplication Avg RangeProcess Owners191-57Super Users20-10Programmers82-22IS Support40-15Infrastructure AvgRangeOperations61-18Tech Services91-28He

9、lp Desk10-8Network10-3Rules Of Thumb :- Application Support EFT/100 Concurrent Users : Average = 8, Range = 4 - 18- Infrastructure Support EFT/1000 SPECmark92 : Average = 3.5, Range = 2 - 6Application support covers staff that deal with user issues regardingapplications, e.g. minor enhancements, bug

10、 fixes, report writing andquestions regarding application functionality. Many companies draw from thesame pool of SAP-skilled resources for both implementation and support.Infrastructure staffing includes technical services personnel such as the Basissupport team, systems programmers, capacity plann

11、ers and performanceexperts. Also included are operations staff such as console operators, jobschedulers and tape operators. We see no great difference in infrastructurestaffing between SAP implementations and other client/server environmentswhen we look at common metrics such as support headcount pe

12、r unit ofcapacity.Two rules of thumb emerge from the selected benchmark data. Total EFT forapplication support is correlated to concurrent users, similar to what wasdone earlier for implementation. Infrastructure support is better correlatedto server capacity since this measures infrastructure size.

13、 The relevantSPECint numbers are drawn from the Unix industry standard SPECmark92benchmark.Variance in infrastructure costs among SAP users is over 3 to 1. (For thetwelve SAP installations, monthly costs per 1,000 dialog steps : range from25 to 90 USD).The hardware costs here include lease, maintena

14、nce and depreciation for allservers. Software includes SAP, DBMS and related software, with purchasecosts depreciated over three years. Staff costs are salaries and benefitsfor the infrastructure staff. Most SAP shops have mirrored their productiondatabase capacity 100 percent and that cost is inclu

15、ded here. Leading-edgeenterprises manage hardware with a centralized, strategic asset managementsystem, which maintains information on location, financials, maintenancestatus and repair history. A hardware asset management organization isinvolved in defining standards, planning for upgrades, negotiating purchaseagreements and planning for disposal.

展开阅读全文
相关资源
正为您匹配相似的精品文档
相关搜索

最新文档


当前位置:首页 > 商业/管理/HR > 企业文档

电脑版 |金锄头文库版权所有
经营许可证:蜀ICP备13022795号 | 川公网安备 51140202000112号